Project Management


Introduction


The objective of the presented case study is to improve the performance of coding in existing projects of IT dept with a cost of £150,000 within 6 months. The purpose is to reduce the number of large computers and hence the overall cost of IT projects. In order to satisfy these criteria, as a manager, there are three scopes that can be the basis of the decision. First is to upgrade/modify the code that suits the personal computers. Second is to re-test the upgraded code so that it works on personal computers. And third is to deploy and operate the upgraded software products. The potential projects are:


1. Online Six Sigma Training Program: Since the CEO wants to train many employees in Six Sigma very quickly; your team thinks it makes sense to provide much of the training in an online format. You have researched several suppliers and you believe you could outsource much of this project.


2. Coding Performance Improvement Project: Even though Megabyte Computers is in the computer industry, the information technology department does not think it uses computing power economically because many programs are not coded for efficiency. The company spends hundreds of millions of pounds for supercomputer and mainframe computing power, and you believe that this project can reduce the number of large computers the company needs.


3. Web Site Redesign Project: The Company’s corporate Web site has grown tremendously in the last few years, and you are not sure that the current design is attracting new customers or meeting current customer needs very well.


4. Wireless Technology Project: There have been great advancements in wireless technologies, and you believe that the company is not taking advantage of developing or using various wireless products.


5. Supporting Office Project: As company is making use of lots of resources for data entry purposes, you believe in setting up a supporting office in developing country like China or India, so that data entry overheads can be reduced to a greater extent.


 


Project Evaluation


Project


Features and


Support and


Ability


Strength and


 


Functionality


Services


(Budget)


Consistency


Online Six Sigma Training Program


collaboration


online access


easy access


manipulation


Web Site Redesign Project


administration


security or personal


costly


can be accurate


Wireless Technology Project


partnership with


availability


average


can adjust


 


telecommunications


of the wireless products


cost


in the changes


Supporting Office Project


security for data


open book with


can be costly


can stand through


 


gathered


limitation


based on the features


the changes


 


 


 


 


 


Multi-Weighted Scores



Bar Chart



 


Result


The project is in favor of Wireless Technology Project, although it cannot promise the strength and consistency because of the impact of changes within the internal and external business environment. The organization needs to fund this type of project in order to achieve the benefits that are available in its features. Based on the evaluation conducted in the project, the collaboration with the telecommunications companies delivers an advantage in the organization in terms of utilizing the wireless technologies. Since every people around the globe has an access in the wireless technologies, it is another opportunity for the organization that should be missed. 


 


Project Proposal 1: Coding Performance Improvement Project (Six Sigma)


 


 


 


Months


 


 


 


Costs


Activities


1


2


3


4


5


6


(£000s)


Define


 


 


 


 


 


 


25


Measure


 


 


 


 


 


 


25


Analyze


 


 


 


 


 


 


25


Improve


 


 


 


 


 


 


25


Control


 


 


 


 


 


 


25


Evaluation


 


 


 


 


 


 


25


 


 


 


 


 


 


 


£150, 000


 


*The activities involved in the Six Sigma project are taken from the learning that is associated in the training.


Project Proposal 2: Continuation of Coding Performance


 


 


 


 


 


Months


 


 


 


 


Costs


Activities


1


2


3


4


5


6


7


8


9


(£000s)


A


 


 


 


 


 


 


 


 


 


25


B


 


 


 



 


 


50


C


 


 


 


 


 


 


 


 


 


50


D


 


 


 


 


 


 



 


 


75


E


 


 


 


 


 


 


 


 


 


50


G


 


 


 


 


 


 


 


 


 


75


H


 


 


 


 


 


 


 


 


 


25


 


*The activities are assumed to be the process of involved in the project


 


The Project Team and Work Breakdown Structure (WBS)


Tasks


People


Tasks Dependencies


Background


Manager 1


Organizational overview


 


HRM


Solid HR practices


 


Stockholder (if necessary)


Trust and credibility


 


Finance Officer


Salient financial status


Features


Web Designer


Virtual effects


 


Encoder


Effective coding solution


 


Advertiser


Promotion, ads, and marketing


Security


Web Designer


Anti-virus, hacks, and others


Interface


Web Master


Dialogue box


Automation


Statisticians


Statistic results


 


Data Analysts


Representation of results


Publication


Manager 2


Publication of the updates


 


Process Breakdown Structure (PBS)


 


 


 


Activities


 


 


 


Week


1


2


3


4


5


6


Team 1


 


 


 


 


 


 


Team 2


 


 


 


 


 


 


Team 3


 


 


 


 


 


 


Team 4


 


 


 


 


 


 


Team 5


 


 


 


 


 


 


Team 6


 


 


 


 


 


 


 


In developing the Gantt chart for the project, it is advised that you should refer to the chart prepared beforehand (Project Proposal 2). It is for the reason that the network of responsibilities of the team and the duration of the tasks are included. The dependencies of the team member are also included in the WBS section of the paper in order to provide the appropriate approach according to the position of the people.



Credit:ivythesis.typepad.com